May 29 - Mentor Training
First Week : June 1 - June 5
Date | Time | Activity | Location |
---|---|---|---|
June 1 | 9:00 am - noon | Welcome : Check in, surveys, Walk around, computer acounts | Claxton 352 |
June 1 | 1:00 pm - 5:00pm | Project assignment, Introduction to Linux and vi | Claxton 352 |
June 2 | 8:30 am - noon | Shuttle to ORNL Check, safety list, walk around | ORNL JICS 5100 |
June 2 | 1:00 pm - 5:00 pm | Overview of project, meet your mentors at ORNL, Makefile, C, Fortran talk | JICS 5100 |
June 3 | 9:00 am - noon | Introduction to Parallel Computing, darter, beacon, rockfrog | Dougherty 406 |
June 3 | 1:00 pm - 5:00 pm | Meet your mentor exercises, project work | Dougherty 406 |
June 4 | 9:00 am - noon | Introduction to MPI Programming | DO 406 |
June 4 | 1:30 pm - 5:00 pm | Exercsies on darter, beacon and rockfrog | DO 406 |
June 5 | 9:00 am - noon | Parallel Programming exercise using MPI | ORNL |
June 5 | 1:30 pm - 5:00 pm | Project work | ORNL |
Second Week : June 8 - June 12
Date | Time | Activity | Location |
---|---|---|---|
June 8 | 9:00 am - 5:00 | Project Science talk I, Project Work | DO 406 |
June 9 | 9:00 am - 5:00 | Project Science talk II, project work | ORNL |
June 10 | 9:00 am - 5:00 | Openmp, openacc, MIC, GPU, Project work | DO 406 |
June 11 | 9:00 am - 5:00 pm | PC cluster building | DO 406 |
June 11 | 4:00 pm - 9:00pm | social gathering | Quarry Trail Apartment pool |
June 12 | 9:00 pm - 5:00 pm | Project work | ORNL/DO 406 |
Third Week : June 15 - June 19
Date | Time | Activity | Location |
---|---|---|---|
June 15 | 9:00 am - noon | Project Work | DO 406 |
June 15 | 1:30 pm - 5;00 pm | Project work | DO 406 |
June 16 | 9:00 am - noon | Project Work | DO 406 |
June 16 | 1:30 am - 5:00 pm | Project work | DO 406 |
June 17 | 9:00 am - 5:00 pm | Project work | ORNL |
June 18 | 9:00 am - noon | Project Work | DO 406 |
June 18 | 1:30 pm - 5:00 pm | Project Work | DO 406 |
June 19 | 9:00 am - noon | Project work | DO 406 |
June 19 | 1:30 pm - 5:00 pm | Project work | DO 406 |
June 19 | 6:00 pm - 9:00pm | social gathering | Quarry Trail Apartment pool |
June 20 | 8:00am | Smoky Mountain Trip (?) | GSMNP |
Fourth Week : June 22- June 26
Date | Time | Activity | Location |
---|---|---|---|
June 22 | 9:00 am - 5:00 pm | Visit talk | DO 406 |
June 23 | 9:00 am - 5:00 pm | Project work | DO 406 |
June 24 | 9:00 am - 5:00 pm | Project work | ORNL |
June 25 | 9:00 am - 5:00 pm | Project work | DO 406 |
June 26 | 9:00 pm - 5:00 pm | Project work | DO 406 |
Fifth Week : June 29- July 3
Date | Time | Activity | Location |
---|---|---|---|
June 29 | 9:00 am - 5:00 pm | Project work | DO 406 |
June 30 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 1 | 9:00 am - 5:00 pm | Project | ORNL |
July 2 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 3 | 9:00 am - 5:00 pm | Holiday | DO 406 |
Sixth Week : July 6- July 10
Date | Time | Activity | Location |
---|---|---|---|
July 6 | 9:00 am - 5:00 pm | Project discussion : Title for poster presentation | DO 406 |
July 7 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 8 | 9:00 am - 5:00 pm | Project overview : 3-slide project summary presentation | ORNL JICS RM 262 |
July 9 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 10 | 9:00 pm - 5:00 pm | Project work | DO 406 |
Seventh Week : July 13- July 17
Date | Time | Activity | Location |
---|---|---|---|
July 13 | 9:00 am - 5:00 pm | Project discussion with Mentors | DO 406 |
July 14 | 9:00 am - 5:00 pm | Zoo Trip | Knoxville Zoo |
July 15 | 9:00 am - 5:00 pm | Project discussion with mentors | ORNL |
July 16 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 17 | 9:00 pm - 5:00 pm | Project work | DO 406 |
Eighth Week : July 20- July 24
Date | Time | Activity | Location |
---|---|---|---|
July 20 | 9:00 am - 5:00 pm | Project discussion with Mentors | DO 406 |
July 21 | 9:00 am - 5:00 pm | Project work : poster preparation | DO 406 |
July 22 | 9:00 am - 5:00 pm | Project work : poster preparation | ORNL |
July 23 | 9:00 am - 5:00 pm | Project work : poster preparation | DO 406 |
July 24 | 9:00 pm - 5:00 pm | Project work : 1st poster : project summary presentation | UTK |
Ninth Week : July 27- July 31
Date | Time | Activity | Location |
---|---|---|---|
July 27 | 9:00 am - 5:00 pm | Project discussion with Mentors | DO 406 |
July 28 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 29 | 9:00 am - 5:00 pm | Project discussion : final presentation | ORNL |
July 30 | 9:00 am - 5:00 pm | Project work | DO 406 |
July 31 | 9:00 pm - 5:00 pm | Project work | DO 406 |
Tenth Week : August 3- August 7
Date | Time | Activity | Location |
---|---|---|---|
Aug. 3 | 9:00 am - 5:00 pm | Project Work | DO 406 |
Aug. 4 | 9:00 am - 5:00 pm | Project wrap up - continuation program | DO 406 Perkins 317 |
Aug. 5 | 9:00 am - 5:00 pm | Final Project presentation JICS auditorium | ORNL |
Aug. 5 | 9:00 am - 5:00 pm | Final Project presentation Due | ORNL |
Aug. 6 | 9:00 am - 5:00 pm | Final Poster presentation with ORAU summer student , closing program at ORNL | ORNL 5200 |
Aug. 7 | 9:00 pm - 5:00 pm | Closing Remarks : Survey | UTK Claxton |